Contractor Left Work Incomplete Dubai? BOQ & Progress Inspection

Renovation QA · Contractor problems

Before you pay again, know what has actually been built.

Work has slowed or stopped, the contractor says the job is 80% complete, and it does not look 80% complete. An independent work progress inspection and BOQ verification gives you a dated, item-by-item record of the site before you release another dirham.

Service
Progress inspection & BOQ verification
Best timing
Before a payment or a takeover
Property types
Villas, apartments, offices, retail, F&B
Our role
We inspect — we never repair
  • Done?What has actually been completed
  • Acceptable?Whether the work passes inspection
  • Paid for?How it compares to BOQ & payments
  • BeforeThe site condition changes

Contractor incomplete work in Dubai

Contractor left the work incomplete in Dubai? Start here

Renovation and construction projects do not always go to plan. You may have paid a contractor to renovate your villa, apartment, office or commercial property, only to discover halfway through that the project is not where it should be.

At this stage, the biggest mistake is to keep paying without first establishing the actual physical and financial status of the project. At Dubai Property Snagging ®, we inspect the visible condition of ongoing or incomplete works, document completed and incomplete items, identify visible defects and compare the site against the documents you make available.

  • Work has slowed down or stopped completely
  • The contractor no longer attends the site
  • Payments have been taken but the work is incomplete
  • The claimed percentage does not match what you see
  • BOQ materials have not been installed
  • Cheaper materials may have been substituted
  • Completed work has visible quality defects
  • Additional payments are requested repeatedly
  • Variation costs keep increasing
  • The completion date has already passed
  • Another contractor is needed to take over
  • You simply do not know how much is really done

First steps

What to do if your contractor leaves the project halfway

Do not immediately appoint another contractor and start changing everything. Document the current condition first. Once someone else starts dismantling, repairing or completing the existing work, proving what the previous contractor actually did becomes much harder.

Before major changes are made, consider recording:

  • Current site condition and status of visible works
  • Incomplete, defective and damaged works
  • Materials available on site
  • Materials that appear to be installed
  • BOQ items completed and not completed
  • Approved variations and unapproved changes
  • MEP status — plumbing, electrical and HVAC
  • Ceilings, flooring and painting
  • Joinery, doors and windows
  • Waterproofing and wet areas
  • Sanitary installations
  • External works and remaining scope

Photos plus item-by-item records create a snapshot you cannot recreate later

A dated report of the site, taken before anyone touches it, becomes the baseline every later conversation refers back to — with the old contractor, the new one, or your lawyer. Condition report →

Construction progress inspection

What is a contractor work progress inspection?

It is an independent site inspection that establishes the visible status of a construction, fit-out or renovation project. Instead of relying on a contractor saying “the project is 75% complete”, the scope is broken down into individual work categories and each one is checked on site.

Work categoryBOQ / contract scopeObserved status
DemolitionIncludedCompleted
BlockworkIncludedSubstantially completed
Electrical first fixIncludedPartially completed
Plumbing first fixIncludedPartially completed
False ceilingIncludedIncomplete
Floor tilesIncludedPartially completed
Bathroom sanitarywareIncludedNot completed
JoineryIncludedNot installed
PaintingIncludedFirst coat only
LightingIncludedNot completed
Testing & commissioningIncludedNot completed
Example onlyThe exact format depends on the project and documents available

BOQ verification Dubai

What is BOQ verification?

A Bill of Quantities (BOQ) lists the work, materials, quantities, units and prices that make up a construction or renovation project. During BOQ verification, those documents are compared with the visible work at the property.

DescriptionQuantityRateAmount
Floor tiles150 m²AED XAED X
Gypsum ceiling120 m²AED XAED X
Wall painting450 m²AED XAED X
Lighting points35 Nos.AED XAED X
Sanitary fixtures8 Nos.AED XAED X

Depending on the agreed scope, each item can be recorded as one of the following. That is very different from walking through and saying the project “looks nearly complete.” BOQ & quantity review

  • Completed
  • Partially completed
  • Not started
  • Installed but defective
  • Installed differently from the specification
  • Missing
  • Replaced by an alternative
  • Concealed — difficult or impossible to verify

Payment verification

Why BOQ verification matters before you make another payment

Progress payments should correspond with contractual milestones and actual progress. Imagine a project worth AED 400,000 where you have already paid AED 320,000. The contractor has received 80% of the contract value — but that does not automatically mean 80% of the physical work is done.

  • 400KContract value (AED)
  • 320KAlready paid (AED)
  • 80%Financial progress
  • ?Physical progress

Some of the most expensive items are often the last to arrive on site:

  • Kitchen joinery and wardrobes
  • Marble and stone
  • Doors
  • Sanitaryware
  • Lighting fixtures
  • AC equipment
  • Smart-home components
  • External landscaping
  • Testing and commissioning
  • Defect rectification

Understanding financial progress takes more than counting rooms that look finished. Where the scope allows, the contract, BOQ, variations, payment schedule and physical progress should be reviewed together. Payment stage verification

Work progress verification

Contractor says 90% complete — how can you verify it?

A percentage should never be accepted just because someone states it. The project is broken into measurable components, and each is reviewed against its visible status.

TradeCivil works

From demolition to the last coat

Demolition, blockwork, plaster, screed, waterproofing, tiling, ceilings and painting.

TradeElectrical

Containment through to testing

Containment, cabling, distribution board, sockets, switches, lighting, fixtures and testing.

TradePlumbing

Pipework, drainage and fixtures

Pipework, drainage, water supply, sanitaryware, water heaters, pumps and testing.

TradeHVAC

Installed is not the same as commissioned

Ductwork, copper piping, drainage, equipment, grilles and diffusers, controls, testing and commissioning.

TradeJoinery

Often the biggest-ticket gap

Kitchen, wardrobes, vanities, doors and feature units.

ResultYour report

A picture a single number cannot give

Component-by-component status is far more useful than one unsupported percentage.

Why it matters: you can ask the contractor specific questions instead of arguing about a number.

Contractor abandoned project Dubai

What if the contractor has completely abandoned the site?

Before a replacement contractor alters anything, arrange a condition and progress inspection. It creates a dated technical record of the site before takeover, documenting:

  • Work apparently completed
  • Partially completed work
  • Outstanding work
  • Visible workmanship defects
  • Damaged areas
  • Installed fixtures and materials
  • Materials remaining on site, where observable
  • Relevant MEP conditions
  • Visible safety concerns
  • Overall condition through photographs

Contractor takeover inspection

Can another contractor finish the work?

Whether you can terminate the existing contract, appoint a replacement, recover costs or withhold amounts depends on your contract and applicable law.

The UAE introduced an updated Civil Transactions Law effective in 2026. Among other changes, the government states that the provisions governing contracts for works were updated to address contractor performance, correction mechanisms, contractual timeframes, termination and completion through another contractor. Every project and contract is different, so obtain appropriate legal advice before terminating a contractor, withholding disputed money or appointing someone else.

Our role is different: we inspect and document the physical condition of the work.

A pre-takeover inspection matters because once a new contractor starts, existing tiles may be lifted, ceilings opened, wiring replaced, waterproofing redone, joinery removed and plumbing altered. After that, separating the original contractor’s work from the replacement contractor’s becomes much harder.

Once the tiles come up and the ceilings come down, nobody can prove who built what.

Dubai Property Snagging ® ®

Renovation inspection Dubai

What can Dubai Property Snagging ® check?

Depending on your project and the agreed scope, the inspection may cover visible aspects of the following.

ScopeCivil & finishing

Surfaces, joinery and finishes

Walls, plaster, paint, flooring, tiles, grout, skirting, ceilings and false ceilings, doors, frames, windows, sealants, joinery, cabinets, countertops, staircases and external finishes.

ScopePlumbing

Supply, drainage and fixtures

Visible supply and drainage installation, sanitaryware, mixers, basins, WCs, showers, water heaters, pumps, visible leakage and water pressure observations where possible.

ScopeElectrical

Accessories, boards and protection

Switches, sockets, lights, distribution boards, visible wiring issues, installed accessories, apparent incomplete work, and RCD/GFCI testing where applicable and safely accessible.

ScopeHVAC

Operation where systems are live

AC operation, cooling and airflow observations, grilles and diffusers, thermostats, visible duct or installation issues, unusual noise and thermal observations where applicable.

ScopeWet areas

Where hidden defects cost the most

Bathrooms, kitchens, balconies, terraces and utility areas — sealant, grouting, drainage, slopes where measurable and moisture indications where accessible.

ScopeBOQ comparison

Documents against the site

Where documents are provided: BOQ item versus visible status, completed, incomplete and missing items, apparent deviations, visible material observations and remaining work.

Thermal imaging and moisture meters support the inspection — they do not replace it

A thermal camera shows temperature anomalies that point to where to look next. It does not see through walls and does not identify every cause on its own. Moisture readings help confirm suspected damp. Thermal imaging inspection →

Renovation progress tracking Dubai

Progress tracking throughout the renovation

You do not need to wait until the contractor disappears. A better approach is to monitor the project during construction with periodic stage inspections. For a substantial villa or apartment renovation, visits are typically planned around these stages.

  • 1

    Existing condition / project start

    Document the property before major works begin.

  • 2

    First fix

    Inspect accessible plumbing, electrical and HVAC work before walls and ceilings close.

  • 3

    Waterproofing

    Review wet areas and accessible waterproofing before tiles cover them.

  • 4

    Civil & finishing progress

    Review ceilings, flooring, wall finishes and other visible work.

  • 5

    Joinery & MEP second fix

    Check installed fixtures, sanitaryware, electrical accessories and joinery.

  • 6

    Pre-handover snagging

    A detailed defect inspection that identifies incomplete and defective works.

  • 7

    De-snagging

    Return after rectification to confirm reported items have been fixed. Timing always follows actual construction progress.

Concealed works

Don’t inspect only at the end

Many critical elements disappear behind finishes. Once tiles, ceilings, cabinets and paint are in place, direct visual inspection may no longer be possible without opening finished surfaces. That is why ongoing inspection is so useful on major renovations — especially waterproofing before tiling.

  • Waterproofing
  • Pipework and drainage
  • Electrical conduits and cabling
  • AC piping
  • Ceiling services
  • Wall services
  • Subfloor preparation
  • Anything behind joinery

BOQ inspection Dubai

BOQ verification is not just about quantity

A proper review answers seven separate questions. They are different questions, and a “yes” to one says nothing about the others.

QuestionHow it is answered
1. Was the item included?Check the original BOQ or contract
2. Was it installed?Inspect the property
3. Is the quantity correct?Measure where reasonably possible and within scope
4. Is it the specified material?Compare visible materials with documentation
5. Is the work acceptable?Inspect visible workmanship
6. Is it complete?Check finishing, connection, adjustment and testing
7. Has it been paid for?Compare against the client’s payment information

Worked example

How an incomplete villa renovation can be assessed

Imagine a villa renovation with a total contract value of AED 600,000. The contractor reports 85% completion and the owner has already paid AED 510,000.

  • 600KContract value (AED)
  • 510KPaid to date (AED)
  • 85%Claimed by contractor

During the inspection, the site may show something like this:

Work itemObserved status
DemolitionCompleted
MasonryCompleted
Ceiling80%
Bathrooms70%
Floor finishes65%
Painting65%
Electrical accessories60%
Doors50%
Kitchen40%
External works30%
Lighting fixtures25%
WardrobesNot installed
AC commissioningIncomplete
Testing & commissioningOutstanding
Defect rectificationOutstanding
ImportantAveraging these does not give a contractual valuation — each BOQ item carries a different value

It does, however, immediately show why a claimed overall percentage needs supporting detail.

Construction quality inspection

What happens when work is completed but defective?

“Completed” and “acceptable” are not the same thing. Progress tracking has to separate the two.

Contractor viewInstalled

100 m² of tiles laid — “100% complete”

The quantity is physically there, so from the contractor’s side the line item is finished and ready to be billed.

Inspection viewNot yet acceptable

The same 100 m² with visible defects

Hollow tiles, uneven levels, poor alignment, inconsistent joints, missing grout, chipped tiles, poor cuts and poor edge finishing.

Why it matters: corrective work is still required before the item can be called satisfactorily complete.

Preparing for the inspection

What documents should you send before the inspection?

More project information allows a more meaningful review. Not every project has all of these — we first review what is available and then define an appropriate scope.

Contract & cost documents

  • Signed contract and approved quotation
  • BOQ and payment schedule
  • Payment receipts
  • Variation orders and approved variations
  • Contractor progress claims
  • Project programme and handover date

Technical & site records

  • Drawings and specifications
  • Material schedule and material approvals
  • Relevant permits and NOCs
  • Previous inspection reports
  • Emails with the contractor
  • Photos from earlier construction stages

No BOQ? An inspection is still useful — but documentation matters

We can still record visible completed, incomplete and defective work. An inspector can observe “wardrobes have not been installed”, but without the contract, quotation or BOQ cannot assume those wardrobes were part of the contractor’s original obligation.

Approvals

Dubai permits and approved works

Construction, alteration, maintenance and fit-out requirements depend on the nature and location of the project and the relevant approving authority. Dubai Municipality maintains building regulations, permit procedures and rules for many construction, modification and maintenance activities, and its Building Permit Procedures include inspection and completion processes for applicable works.

Depending on the property, approvals or NOCs may also be needed from a developer, community manager or building management. Confirm your contractor has obtained the approvals required for the work being performed.

Red flags

Warning signs your renovation needs an independent inspection

  • Deadlines are repeatedly missed
  • Workers suddenly stop attending site
  • Progress becomes very slow
  • Large advance payments are requested
  • Payment requests run ahead of progress
  • Detailed progress information is refused
  • BOQ quantities appear inconsistent
  • Materials are being substituted
  • Work is covered before you can inspect it
  • Waterproofing is about to be covered
  • Obvious workmanship defects are visible
  • Variation costs keep increasing
  • Subcontractors blame each other
  • Completion is claimed while work remains
  • Testing and commissioning were not performed
  • Snagging items are repeatedly ignored
  • The relationship is deteriorating
  • You are considering terminating the contract
  • A replacement contractor is about to start
  • You are overseas and cannot monitor the site

Controlling payments

A better way to control renovation payments

Documented milestones give the owner considerably more visibility. The exact payment structure should always follow the agreed contract.

The usual cycle

  • Contractor requests money
  • Owner pays
  • Contractor continues
  • Problems surface at handover — after the money has gone

A controlled cycle

  • Milestone 1: specified work completed → inspection → payment decision
  • Milestone 2: specified work completed → inspection → payment decision
  • Milestone 3: specified work completed → inspection → payment decision
  • Final: de-snagging → final payment decision

Ongoing snagging Dubai

Ongoing renovation & construction inspection — who it is for

Independent inspection is not only for failed projects. It helps good projects stay organised, so owners see what has been done, what remains, what has defects and what is about to be concealed.

  • Villa renovations
  • Apartment renovations
  • Luxury fit-outs
  • Office fit-outs
  • Restaurant fit-outs
  • Retail projects
  • Holiday-home renovations
  • Landlords upgrading investment properties
  • Overseas owners managing projects remotely
  • Owners changing contractors midway
  • Projects that are already delayed
  • Projects with repeated variation requests

60 questions answered

FAQs: contractor problems, progress tracking & BOQ verification in Dubai

When the contractor stops or abandons the job

What should I do if my contractor stops working halfway through my renovation?

First document the project’s present condition. Avoid allowing substantial new work to change the site before existing work, incomplete items and visible defects have been recorded. Then review your contract and consider legal advice before formally terminating or replacing the contractor.

Can Dubai Property Snagging ® inspect an unfinished renovation?

Yes. An inspection can be tailored to unfinished or partially completed renovation work, subject to access, safety and the agreed inspection scope.

Can you inspect work before another contractor takes over?

Yes. This is one of the most useful times to perform a condition and progress inspection.

Why should I inspect before appointing another contractor?

Because the replacement contractor may remove or modify the existing work, making the original condition difficult to document later.

What if the contractor is not responding to me?

Preserve all communication, including emails, WhatsApp messages, payment receipts, quotations, invoices and site records. Consider obtaining a current site-condition report before the property changes substantially.

What if I paid cash?

Retain any receipts, invoices, acknowledgements, conversations or other proof relating to payments, and seek legal advice if there is a financial dispute.

Can you inspect a project where no work has happened for months?

Yes, subject to site access and safety.

What is a takeover inspection?

A takeover inspection records the condition and apparent progress of a project before responsibility for continuing work transfers to another contractor.

Should the new contractor inspect the old contractor’s work?

The replacement contractor will normally need to understand the existing condition before continuing. An independent report provides an additional documented snapshot before takeover.

What if the previous contractor’s defective work has to be demolished?

Document its condition before demolition where reasonably possible. Photographs, measurements and written observations can become important later.

Progress, percentages & payments

Can you determine how much work the contractor has completed?

We assess and document the visible status of work items and, where appropriate documentation is available, compare those observations against the BOQ or agreed scope.

Can you verify whether the contractor’s claimed progress percentage is correct?

We compare claimed progress against visible site conditions and available project documentation. Complex financial certification or formal contractual valuation may require the appropriately appointed professional.

Can I arrange an inspection before paying my contractor?

Yes. A progress inspection before a payment milestone helps you understand the visible project status before making a commercial decision about further payment.

Can the inspector tell me how much money I should pay?

An inspection provides technical observations and progress information. The amount legally or contractually payable depends on the contract, valuation basis, variations and other circumstances.

My contractor says the villa is 90% complete. Can this be checked?

Yes. The work is broken into individual categories and reviewed against the available BOQ, scope and visible progress rather than relying on an overall percentage.

What if my contractor has taken more money than the work completed?

The technical report documents physical observations. The contractual or financial consequences should then be reviewed against the contract, payment records and, where appropriate, professional or legal advice.

What if the contractor wants full payment before snagging?

Review the contract carefully. A pre-completion inspection can identify outstanding and defective work before you make further payment decisions.

Should I pay for materials that have not reached the site?

This depends on your contractual payment arrangements. An inspection can confirm whether particular materials are visibly present on site at the time, but contractual entitlement should be assessed separately.

Can you verify materials stored off-site?

A normal property inspection cannot automatically verify materials said to be stored elsewhere. Separate arrangements and documentation would be necessary.

Can you check the contractor’s invoices?

Invoices, BOQs and payment records provide useful background for comparison. Formal accounting, legal entitlement or certified valuation is separate from a standard technical property inspection.

BOQ, quantities, materials & variations

What is BOQ verification?

A comparison of Bill of Quantities items against the work and materials that can reasonably be verified at the property within the agreed scope.

Why is BOQ verification important?

It helps an owner understand which contracted items appear completed, incomplete, missing or different from the available documentation.

Can you check whether the contractor used cheaper materials?

Where materials are visible and reasonably identifiable, they can be compared against provided specifications or approved material information. Concealed or unidentifiable materials may require separate documentation or specialist testing.

Can you check tile quantities?

Measurements and visible installed areas may be compared with BOQ information where measurement verification forms part of the agreed scope.

Can you verify paint quantities?

Completed painted areas may be measured or assessed where appropriate, but verifying the actual volume of paint consumed is different from measuring finished painted areas.

Can you check false ceiling quantities?

Accessible ceiling dimensions and status may be reviewed against the BOQ where measurement verification is included.

Can you check whether sanitaryware is missing?

Yes. Provided the schedule or BOQ is available, installed items can be compared with expected items.

Can you verify kitchen and wardrobe installation?

Visible installed joinery may be compared against supplied drawings, schedules or BOQ information within the inspection scope.

Can you verify variation works?

Approved variation documents can be compared against visible executed work within the agreed scope. Variation order review

What is a variation order?

A variation is generally a change, addition or omission from the originally agreed scope, usually documented together with any resulting cost or programme implications.

Should I accept verbal variations?

For clarity and record-keeping, project changes are better documented in writing, including scope, price and implications. Obtain contract-specific advice where required.

Can you check whether variation work was actually completed?

Yes, if the variation documentation is provided and the resulting work is visible and within the inspection scope.

Trades, hidden work & inspection tools

Can you identify incomplete work?

Yes, where the intended scope is known and the work is visible or reasonably accessible.

Can you identify defective workmanship?

Visible defects within the inspection scope can be documented.

Can you inspect only MEP works?

Yes. A specific scope can be agreed for accessible mechanical, electrical and plumbing elements.

Can you inspect civil works only?

Yes. The scope can focus on finishes, flooring, walls, ceilings, doors, joinery and other visible civil and architectural items.

Can you check plumbing work?

Visible and accessible plumbing components can be inspected within the agreed scope.

Can you check electrical work?

Accessible electrical components and relevant functionality can be reviewed according to the agreed scope and safe test conditions.

Can you check AC work?

Accessible HVAC components and operation can be assessed where systems are available and operational.

Can you check waterproofing?

Accessible waterproofing can be inspected during construction. Once it is covered by finishes, direct visual verification becomes limited.

Should waterproofing be inspected before tiling?

Yes. Waterproofing is a clear example of a construction layer that becomes concealed once finishes are installed. Waterproofing inspection

Can you compare today’s condition with old photographs?

Where reliable photographs or previous reports are provided, they can give useful background, although conclusions depend on the quality and context of that evidence.

What if some work is hidden behind ceilings and walls?

A standard visual inspection cannot verify every concealed component. Previous photographs, approved drawings, testing or intrusive investigation may be required depending on the issue.

Can thermal imaging detect hidden defects?

Thermal imaging identifies temperature anomalies that support further investigation. It does not see through walls and does not automatically identify the exact cause of every anomaly.

Can a moisture meter be used?

Yes. Where relevant, moisture readings help investigate suspected moisture conditions.

Reports, legal questions & permits

Will you take photographs?

Yes. Photographic documentation is an important part of the inspection report.

Can the report show completed and incomplete items separately?

Yes. The report can distinguish observations relating to completed, incomplete and defective work where appropriate.

Can your report be used as evidence?

An inspection report is a technical record of observations made at the time of inspection. Whether it is admissible, sufficient or relied upon in legal proceedings should be discussed with your lawyer.

Is your inspection a court expert report?

A standard property inspection should not be assumed to be a court-appointed expert report. Court proceedings may involve specific expert appointment and procedural requirements.

Can you decide whether the contractor breached the contract?

We document technical conditions. Legal determination of breach is a contractual and legal matter.

Can Dubai Land Department resolve my renovation contract dispute?

Not necessarily. DLD states that contractual claims and applications involving revocation, refunds or indemnity are outside the scope of its Real Estate Violation System and may require judicial review.

Can you tell the contractor how to repair defects?

Reports describe observations and defects. Detailed repair design, engineering solutions or method statements may require the appropriate specialist.

Can you check whether the renovation follows approved drawings?

Visible site conditions can be compared with drawings supplied for the inspection where this is in the agreed scope. Formal regulatory compliance certification is a separate matter.

Do renovation works in Dubai require permits or NOCs?

Requirements depend on the work, property and authority. Dubai Municipality regulates many building, alteration and maintenance activities, and individual developments may have additional developer or building-management requirements.

Ongoing inspection & working with us

Can you inspect a contractor’s renovation every week?

Periodic inspection programmes can be arranged depending on the project, required scope and construction programme.

How frequently should renovation work be inspected?

It depends on project complexity. Inspections are most valuable before important work becomes concealed and before major payment or completion milestones.

Can you track progress until project completion?

Yes. An ongoing arrangement can be structured with periodic visits and reports through the project’s key stages.

Can overseas property owners use this service?

Yes. Progress reports and photographic documentation give overseas owners independent information about the site’s visible status.

Can you attend meetings with my contractor?

This depends on the agreed scope. Technical observations from the inspection also help owners ask more specific questions in contractor meetings. Owners representative

When is the best time to contact Dubai Property Snagging ®?

Ideally before you make another major payment, before defective work is covered, before another contractor takes over, or as soon as you become concerned about progress or workmanship.

How we can help

Contractor left your project incomplete?

If your contractor has stopped working, your project is delayed, or you want to verify the BOQ before releasing another payment, arrange an independent inspection before the existing site condition changes.

Inspection services

  • Contractor work progress inspection
  • Incomplete work & pre-takeover inspection
  • Contractor takeover condition report
  • MEP and civil & finishing inspection
  • Thermal & moisture assessment
  • De-snagging & final completion inspection

Important note

Property inspection and BOQ comparison provide technical observations based on the accessible condition of the property and the documents provided for the agreed scope. They are not legal opinions, court expert reports, statutory approvals, structural certifications, formal quantity-surveyor valuations or contractual determinations unless those services are separately appointed. For contract termination, recovery of money, damages, withholding payments or legal proceedings, obtain appropriate legal advice.

Before you pay more or appoint another contractor, know exactly what has been done

Work progress, BOQ items, visible defects and remaining scope — documented item by item in a numbered photographic report. Inspect before you invest. We inspect — we never repair.

DED Certified · RERA Approved · InterNACHI Certified · 98,000+ Inspections

author avatar
Dubai Property Snagging ®
#1 Property Snagging Company in UAE Fully certified by DED, approved by RERA, and proudly InterNACHI-accredited. ✅ 98,000+ Snagging Inspections Completed Across the UAE
Share Article